Sot Saltification Boiler Energy Efficiency Test and Price Comparison Document (Second Round of Price Comparison)
Category: Bidding
Release time: 2026-09-03
Summary:
1. Price Comparison Conditions
This quotation pertains to the energy‑efficiency testing of Boilers No. 3 and No. 4 at Sote Salt Chemical Co., Ltd. The project has been approved by Chongqing Sote Salt Chemical Co., Ltd., with Chongqing Sote Salt Chemical Co., Ltd. serving as the project owner. The project now meets the conditions for price comparison, and we hereby invite quotations through a request‑for‑quotation process.
2. Project Overview and Scope of Price Comparison
2.1 Project Location: Chongqing Sote Salt Chemical Co., Ltd.
2.2 Project Scope: Energy efficiency testing of Boilers No. 3 and No. 4 at Chongqing Suote Salt Chemical Co., Ltd., encompassing the preparation of the test plan, on-site testing, sample collection and laboratory analysis, data processing and calculations, problem diagnosis and analysis, preparation and delivery of the final report, as well as technical briefing—details are provided in the Technical Specifications.
2.3 Service Duration: From the effective date of the contract until completion of on-site testing and submission of the formal report, the total duration shall not exceed 90 calendar days; any delays caused by unit‑related scheduling or shutdowns shall result in an extension of the service period.
2.4 Project Scope: Energy efficiency testing of Boilers No. 3 and No. 4 at Chongqing Suote Salt Chemical Co., Ltd., including the preparation of the test plan, on-site testing, sample collection and laboratory analysis, data processing and calculations, problem diagnosis and analysis, preparation and delivery of the final report, and technical briefing; for details, please refer to the Technical Specifications.
2.5 Quality Assurance: A 12-month warranty period shall apply from the date of report delivery; during the warranty period, if testing method errors or calculation errors are identified, the bidder shall conduct retesting at no charge and issue a corrected report.
2.6 The total control price for this procurement is set as follows: the total control price for the energy efficiency testing of Boilers No. 3 and No. 4 is RMB 110,000; any bid with a total quoted price exceeding this control price shall be deemed invalid.
3. Qualification Requirements for Bidders
3.1 An independent legal entity registered within the territory of China; the bidder shall hold the Approval Certificate for Special Equipment Inspection and Testing Institutions of the People’s Republic of China (for inspection institutions), with the scope of approval including GD2; the bidder shall also possess the Accreditation Certificate for Inspection and Testing Institutions (CMA).
3.2 The project leader must hold a Level II Inspector Certificate for Boiler Energy Efficiency Testing (TSG Z8002) and have experience leading energy efficiency testing projects for power plant boilers; on-site testing personnel must possess an energy efficiency testing operation certificate; no unqualified personnel are permitted to perform testing activities.
3.3 Within the past 36 months, the bidder shall have completed at least three energy‑efficiency or performance test projects for power‑station boilers of the same capacity class. The bid documents must include photocopies of key contract pages and report cover pages; industrial boiler performance records will not be accepted as substitutes.
3.4 The bidder shall possess a complete set of testing instruments and equipment, all of which must be within their valid metrological verification period. The bidder shall submit an instrument inventory and copies of the corresponding metrological certificates. The use of externally borrowed equipment lacking metrological traceability for formal testing is strictly prohibited.
3.5 The applicant has a sound financial standing, sufficient assets and capabilities, and the ability to perform the contract effectively.
3.6 Construction personnel must be covered by insurance with a minimum coverage of RMB 800,000 per person (except for those already enrolled in the Employer’s social insurance). Workers shall wear uniform work attire as required by the Employer, and all personnel engaged in special operations must hold valid certifications to perform their duties.
4. Quotation Deadline
Deadline: September 7, 2026, 9:30 a.m. (Beijing Time)
5. Contact Information
Price Comparator: Chongqing Sote Salt Chemical Co., Ltd.
Address: No. 98, Longxiang Avenue, Wanzhou District, Chongqing City
Contact: Sun Tongying
Phone: 13517321268
Disclaimer: The official platform for publishing this tender information is the official website of Chongqing Xiangyu Salt Chemical Co., Ltd. at http://www.cqxyyh.com. Except for this channel, our company has not published any tender information on any other websites, forums, or platforms. Any tender notices reproduced on other media that cite our company as the tendering entity are unauthorized reproductions and are deemed invalid; we reserve the right to pursue legal action.
Keywords: Sot Saltification Boiler Energy Efficiency Test and Price Comparison Document (Second Round of Price Comparison)