New Price Comparison Document for the Installation of Sealed Water Coolers and Associated Piping Works

Category: Bidding

Release time: 2024-11-28

Summary:

1. Price comparison conditions
This quotation covers the installation and piping work for the newly added sealed water cooler at Chongqing Xiangyu Salt & Chemical Co., Ltd.
Approved by Chongqing Xiangyu Salt & Chemical Co., Ltd., the project owner is Chongqing Xiangyu Salt & Chemical Co., Ltd. The project now meets the conditions for price comparison, and we are hereby inviting quotations and bids for this project.
2. Project Overview and Price Comparison Scope
2.1 Project Location: Within the premises of Chongqing Xiangyu Salt & Chemical Co., Ltd.
2.2 Project Scope: The installation and piping construction works for the newly added sealed water cooler at Chongqing Xiangyu Salt & Chemical Co., Ltd.: including the installation of pressure vessels and associated piping. For detailed specifications, please refer to the Bill of Quantities. This project is an installation and construction undertaking that covers auxiliary materials (including welding electrodes, welding wires, oxygen, acetylene, argon, etc.), tools and equipment, lifting operations, non-destructive testing, supervision and inspection, and other related activities. For specific details, please refer to the Bill of Quantities.
2.3 Construction Period: Completion within 30 calendar days from the start date notified by Party A (excluding coordination meetings; the specific start date will be determined based on Party A’s production schedule).
2.4 Project Scope: The installation and piping work for the newly added sealed water cooler at Chongqing Xiangyu Salt & Chemical Co., Ltd.: including pressure vessel installation and piping. For detailed specifications, please refer to the Bill of Quantities. This project is an installation and construction undertaking that covers auxiliary materials (including welding electrodes, welding wires, oxygen, acetylene, argon, etc.), tools and equipment, lifting operations, non-destructive testing, and utilities such as electricity and water. For specific details, please refer to the Bill of Quantities.
3. Qualification Requirements for Bidders
3.1 For this price comparison, bidders must possess a valid Grade III or higher general contracting qualification for petrochemical engineering construction issued by the competent construction administrative authority, as well as an industrial pipeline installation license of Grade GC1 or higher, or a Class A pressure vessel qualification. They must also have the requisite construction capabilities in terms of personnel, equipment, and financial resources.
3.1 This price comparison requires bidders to hold a valid safety production license.
3.1 Prior to the bid submission deadline, bidders must have completed at least one construction project in equipment installation or maintenance within the petrochemical industry over the past four years (from January 1, 2020, to the bid submission deadline).
4. Quotation deadline
Deadline: 5:00 PM, December 2, 2024 (Beijing Time)
5. Contact Information
Price Comparison Person: Chongqing Xiangyu Salt & Chemical Co., Ltd.
Address: No. 98, Longxiang Avenue, Wanzhou District, Chongqing City
Contact: Sun Tongying Phone: 13517321268

 

Disclaimer: The official platform for our company’s announcement of this tender is the website of Chongqing Xiangyu Salt & Chemical Co., Ltd.: http://www.cqxyyh.com. Apart from this, our company has not published any tender information on any other websites, forums, or media platforms. Any tender information reproduced from other sources and attributed to our company as the tendering entity is unauthorized and therefore invalid. We reserve the right to pursue legal action against such unauthorized reproductions.