2025 Xiangyu Salt & Chemical Pressure Pipeline First Inspection DR Digital Radiography Tender Document
Category: Bidding
Release time: 2025-05-07
Summary:
1. Price comparison conditions
This quotation pertains to the first inspection of pressure pipelines for 2025 conducted using DR digital radiography, which has been approved by Chongqing Xiangyu Salt & Chemical Co., Ltd. The project owner is Chongqing Xiangyu Salt & Chemical Co., Ltd., and the project now meets the conditions for competitive bidding. We are hereby inviting quotations and conducting a comparative price inquiry for this project.
2. Project Overview and Price Comparison Scope
2.1 Project Location: Within the premises of Chongqing Xiangyu Salt & Chemical Co., Ltd.
2.2 Project Scope: First inspection of pressure pipelines within the premises of Chongqing Xiangyu Salt & Chemical Co., Ltd. in 2025, using DR digital radiography testing.
2.3 Contract Term: One year from the date on which the contract is signed and becomes effective.
2.4 Project Scope: Digital Radiography (DR) inspection of pressure pipelines within the premises of Chongqing Xiangyu Salt & Chemical Co., Ltd. for their first inspection in 2025. During the contract period, Chongqing Xiangyu Salt & Chemical will cooperate with various inspection agencies to carry out DR digital radiography testing on the pressure pipelines subject to the first inspection, ensuring that the scheduled periodic inspections of these pipelines are completed on time.
3. Qualification Requirements for Bidders
3.1 An independent legal entity registered within the territory of China;
3.2 Hold the Approval Certificate for Special Equipment Inspection and Testing Institutions of the People’s Republic of China issued by the Administration for Market Regulation (Non-Destructive Testing Institution), the Qualification Certification for Inspection and Testing Institutions and its attachments (approved to engage in radiographic testing (RT), ultrasonic testing (UT), magnetic particle testing (MT), penetrant testing (PT), time-of-flight diffraction ultrasonic testing (TOFD), and other related inspection activities), or the Level Assessment Certificate for Non-Destructive Testing Institutions for Special Equipment.
3.3 Hold a radiation safety license issued by the environmental protection authority;
3.4 Hold certification certificates for quality, environmental, occupational health, and safety management systems;
3.5 Sound financial condition, with sufficient assets and capabilities to effectively perform the contract;
3.6 This price comparison requires bidders to assign the following personnel:
3.6.1 The project manager or site supervisor holds a Level II certification for radiographic (RT(D)) inspection and testing personnel specializing in special equipment.
3.6.2 Professional inspectors hold the Practicing Registration Certificate for Special Equipment Inspection and Testing Personnel, Level II for Radiographic Testing (RT(D)).
3.7 This quotation does not accept joint venture bids.
4. Inspections required by the contracting party:
4.1 The contracting party shall notify the winning bidder, within one week prior to the inspection, of the workload and requirements for the project inspection task. Upon receiving the task, the winning bidder must complete the inspection task in accordance with the contracting party’s requirements and scheduled milestones. Any defects discovered during the inspection process shall be promptly reported back to the contracting party. Within one week after completion of the entire project inspection, the winning bidder shall submit a valid inspection report to the contracting party.
4.2 Qualification review method for this price comparison: post-qualification review;
4.3 Price Comparison Quotation Requirements:
4.3.1 The total price shall be calculated based on the lowest unit price, provided that the requirements of the Employer are met. (See Appendix)
4.3.2 Radiographic Testing: Quoted at a unit price based on the nominal diameter of the component being inspected.
4.3.3 Settlement Method: The settlement amount shall be the product of the actual quantity verified on-site by both parties and the unit price agreed upon in the contract.
4.4.4 After Party A receives Party B’s inspection report and invoice and posts them to its accounts, Party A shall pay the fee for each batch in a single lump sum within two months. The payment method is bank acceptance.
4.4.5 The quotation includes the bidder’s labor costs, travel expenses, material costs, equipment usage fees, and taxes—and is not limited to these expenses. The contracting party will no longer pay any additional fees separately.
4. Quotation deadline
Deadline: 2:30 p.m. (Beijing Time), May 12, 2025
5. Contact Information
Price Comparison Person: Chongqing Xiangyu Salt & Chemical Co., Ltd.
Address: No. 98 Longxiang Avenue, Wanzhou District, Chongqing City
Contact: Sun Tongying
Phone: 13517321268
Disclaimer: The official platform for our company’s announcement of this tender is the website of Chongqing Xiangyu Salt & Chemical Co., Ltd.: http://www.cqxyyh.com. Apart from this, our company has not published any tender information on any other websites, forums, or media platforms. Any tender information reproduced from other sources and attributed to our company as the tendering entity is unauthorized and therefore invalid. We reserve the right to pursue legal action against such unauthorized reproductions.
Keywords: 2025 Xiangyu Salt & Chemical Pressure Pipeline First Inspection DR Digital Radiography Tender Document
Relevant information
-
Selection Document for the Settlement Audit of the Access Road and Site Grading Works for Well ZK101 in the Xinfeng Mining Area Rock Salt Exploration Project of Chongqing Sote Salt Chemical Co., Ltd.
Time:2026-11-10
-
Inquiry Letter for Rail Transport of Calcination Kiln Support Rollers (Wanzhou–Sanmenxia)
Time:2026-11-09
-
Price Comparison Document for the Installation of a Liquid Oxygen Pump with DC Busbar at Chongqing Xiangyu Salt Chemical Co., Ltd. (Second Price Comparison)
Time:2026-11-09
-
Topographic Map and Boundary Survey Bidding Documents for the Waste Salt Recovery and Comprehensive Utilization Project (Second Price Comparison)
Time:2026-11-09
-
Price Comparison Document for Outsourced Processing between Chongqing Xiangyu Salt Chemical and Sote Salt Chemical
Time:2026-11-09